Roadwork update: R 77 milling finished; asphalt expected by Memorial Day weekend
May 12, 2026
County staff reported that milling on R 77 (north 7 miles on Highway 175 from Shore County) finished about a week earlier and asphalt lifts are expected to be completed by Memorial Day weekend, with final work by June 1.
The full story
An agency official reported progress on roadwork for R 77: milling finished roughly a week ago and the first HMA lift was completed the prior Thursday; one lane of intermediate has been paved and crews planned to complete the asphalt portion by Memorial Day weekend, with shoulder painting to follow and final completion anticipated by June 1.