Roadwork update: R 77 milling finished; asphalt expected by Memorial Day weekend

May 12, 2026

County staff reported that milling on R 77 (north 7 miles on Highway 175 from Shore County) finished about a week earlier and asphalt lifts are expected to be completed by Memorial Day weekend, with final work by June 1.

The full story

An agency official reported progress on roadwork for R 77: milling finished roughly a week ago and the first HMA lift was completed the prior Thursday; one lane of intermediate has been paved and crews planned to complete the asphalt portion by Memorial Day weekend, with shoulder painting to follow and final completion anticipated by June 1.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in