Council hears engineering plan and 12–15 month timeline for a second water source
Aug 12, 2026
Sunrise Engineering told Laketown the process to develop a second well would include water-rights work, a Preliminary Evaluation Report, drilling and multi-stage pump testing; the firm estimated 12–15 months after funding approval and two candidate well sites were discussed.
The full story
Scott Archibald of Sunrise Engineering presented a step-by-step plan for developing a second water source for Laketown, laying out permitting, testing and construction tasks the town would need to complete. Archibald said work would include a Preliminary Evaluation Report, coordination with the Division of Drinking Water and Division of Water Rights, well drilling, step and 24-hour pump tests and well-house construction to connect a new source to the town system.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →