Council hears engineering plan and 12–15 month timeline for a second water source

Aug 12, 2026

Sunrise Engineering told Laketown the process to develop a second well would include water-rights work, a Preliminary Evaluation Report, drilling and multi-stage pump testing; the firm estimated 12–15 months after funding approval and two candidate well sites were discussed.

The full story

Scott Archibald of Sunrise Engineering presented a step-by-step plan for developing a second water source for Laketown, laying out permitting, testing and construction tasks the town would need to complete. Archibald said work would include a Preliminary Evaluation Report, coordination with the Division of Drinking Water and Division of Water Rights, well drilling, step and 24-hour pump tests and well-house construction to connect a new source to the town system.