Evergreen Elementary project on schedule; GMP 3 to set full budget

Enumclaw School District Board of Directors · August 17, 2026

Summary

A presenter told the Enumclaw board that Evergreen Elementary construction is progressing ahead of schedule, with footings poured and prefabrication underway; three contract amendments executed and GMP 3 (full guaranteed maximum price) will be presented at the next board meeting.

The Evergreen Elementary project is advancing quickly, project staff told the board. "The project is moving along extraordinarily well," the presenter said, noting footings are poured in most areas, formwork is in place and prefabrication of walls is starting.

Project staff reported that the 100% design development set has been received, three contract amendments have been executed (including validation-phase work) and two GMPs are already in place. The presenter said GMP 3, which will encompass the full project budget under the progressive design-build approach, will be presented at the next board meeting so the board will know the total cost.

Board members asked about design details and timing; 90% construction documents are scheduled for Oct. 19 and 100% construction documents are expected shortly thereafter, with mid-to-late December noted as a target for the final set. The presenter and superintendent emphasized the tight schedule and risk monitoring, including commissioning before and during occupancy to ensure the building is turnkey for students and staff.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source