Board reviews long‑range plan; gatehouse, monuments and well projects require permits and bidding

River Ridge Community Development District Board of Supervisors · April 28, 2026

Summary

The Board reviewed a revised long‑range plan that includes completed traffic calming ($26,739), a nearly completed $291,500 backup irrigation well, monument replacements ($250,000 estimate) and gatehouse renovation costs that will require sealed bidding; CIP changes may require a ~$2.5 million loan.

Eric Long presented a revised Long Range Plan and reported that a traffic calming project (radar sign and camera) was completed at $26,739. He said a backup irrigation well costing $291,500 is near completion and that staff expects pump installation within weeks and subsequent water quality testing.

Long also reviewed estimated costs for monument replacement ($250,000) and gatehouse renovations (estimated $615,775 for FY2026 and $407,240 for FY2027). He said gatehouse projects exceed the $550,000 sealed‑bid threshold and that permits will be submitted to the Village of Estero; SFWMD approval for the stormwater management element is still pending. Long stated the CIP change will likely necessitate a construction loan of approximately $2.5 million.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source