Ellen Ware culvert work underway; FEMA advance-payment delay could affect timing
Summary
Work to replace a culvert on Ellen Ware Road began the week of Aug. 22 and is expected to take about three weeks; the Selectboard was told FEMA is approximately four weeks behind on approving the advance payment and said FEMA would reimburse any interest charged because of the delay.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Selectboard heard that a culvert replacement on Ellen Ware Road began the week of Aug. 22 and is expected to last about three weeks; the road is closed to through traffic during the work. Highway Supervisor E. Mark Bills reported the schedule and ongoing road maintenance activities.
Bills also told the board that FEMA is about four weeks behind in approving an advance payment for the Hill Road repairs; once FEMA approves, payment may take an additional four weeks. According to the board’s report of a FEMA representative, the agency indicated it would reimburse the town for any interest incurred because of the approval and payment delay. Selectboard members discussed the possibility of celebrating the reopening after Hill Road paving, guardrail installation, and final cleanup are complete.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.