Permanent Building Commission updates Facilities Master Plan, Middle School planning delayed
Sep 2, 2026
Sep 2, 2026
The Permanent Building Commission reported progress on HVAC and roofing work at the high school, noted delays to Middle School planning due to site constraints, and recommended a new Firehouse 1 at the annex site; community survey responses were reviewed.
The full story
Kevin Goff, chairman of the Permanent Building Commission, and Vice Chairman Glenn Neilson updated the Board of Selectmen on the Facilities Master Plan and school projects. At the High School the HVAC rooftop project has exterior work completed and controls are being installed prior to commissioning; the High School roofing project has a recommended contractor and materials are expected to require a roughly 60-day lead time followed by about 120 working days of construction.