Board approves $7,700 partial payment for Arrowhead change order after discussion

Sep 3, 2026

Board approved a change order for the Arrowhead project; staff said the original accepted bid was $60,186.19, the contractor proposed $10,266.61 in changes, and staff recommended paying $7,699.90 to settle the request and preserve the contractor relationship.

The full story

The board examined a contractor change order for the Arrowhead project (attachment 6e). Staff said the original accepted bid was $60,186.19 and that the contractor proposed a $10,266.61 change order. Staff requested approval to pay $7,699.90 (transcribed as "$7,699 and $90.96 cents") to bring the project total to $67,886.15; this figure accounts for added vaults, an unlocatable line and other unforeseen difficulties.