Whitingham sets RFP timetable: issue Sept. 3, questions due Sept. 10, bids open Sept. 17
Summary
The Selectboard set an expedited RFP timeline for the highway garage project: the RFP will be posted Sept. 3; prospective bidders should direct questions to consultant Jon Saccoccio by Sept. 10; and bids will be opened via Teams at 5 p.m. on Sept. 17.
Get email alerts on the Procurement Timeline topic
No spam. Unsubscribe anytime.
The Whitingham Selectboard fixed key dates for the highway garage RFP at its Sept. 2 special meeting. The board directed that the RFP be issued on Sept. 3 and that prospective bidders submit questions to consultant Jon Saccoccio by Sept. 10; Saccoccio will answer questions and share responses with all potential bidders.
Staff will post the RFP on the state bid website, Dodge, and one additional site; bids will be opened at 5 p.m. on Sept. 17 in a Teams meeting. The board selected work schedule 2a for the project and decided not to evaluate alternatives 2b and 2c, citing contractor availability and a desire to accelerate the schedule.
The minutes record a contingency: if construction is not fully complete by November, trucks should be able to park in the new garage but tools may remain in Connex storage boxes for a longer period. The Selectboard recorded that the final RFP draft reflecting these timeline and scope decisions would be reviewed and approved at the regular Selectboard meeting later that evening.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.