Board approves $100,000 change order for Jefferson Smith Civic Center soils and authorizes payment release

Sep 2, 2026

Commissioners approved change order no. 7 to address unsuitable soils at the Jefferson Smith Civic Center; staff said negotiations reduced the contractor’s claim to about $100,000 and authorized the clerk to release payment to meet grant closeout deadlines.

The full story

Staff told commissioners the civic center site required removal of unexpected clay and unsuitable soils. Engineers initially submitted a change order near $135,000; staff negotiated the scope and cost and said the net contractor request and overhead/profit brought the amount to roughly $105,000. "They initially submitted us about $135,000 change order ... we did get it down under 100,000 ... and then their overhead and profit brought it up to the 105," Mr. Furry said.