Franklin High School project shows progress; contractors share drone model and schedule
Oct 22, 2025
Carol Daniel Construction presented drone footage and a 3-D model showing foundations, roofing progress and a new student parking area already turned over; contractors said they expect to complete key slabs and interior work over the next months.
The full story
Dave Gotwold and Josh Cochran of Carol Daniel Construction briefed the joint session with a drone-based 3-D flyover and timeline for Franklin High School and the adjacent stadium. Gotwold described exteriors on several buildings as nearly closed in, roofing underway and a sizable foundation "box" for the stadium approaching full placement.