The Board approved Escrow Release #1 for Hellings Builders—Howell Ridge Development in the amount of $218,513.00, leaving a balance of $469,986.35; Township engineer reported incomplete silt-sock installation at two house sites and said the contingency is held until project completion.

The full story

Dan Wright, the Township engineer, explained his office withheld part of the requested escrow release following inspection and recommended a partial release of $218,513.00 for the Howell Ridge development. Wright said his office requested additional silt fence and silt sock at specified locations and that the entire contingency is held until the project’s completion; after the partial release the escrow balance would be $469,986.35.