Board updates schedule and costs for final reconstruction phase; phase‑3 material on site

Aug 25, 2026

Board staff said phase 2 of the reconstruction is complete, phase 3 materials and 15‑inch tile are on site, and the anticipated phase‑3 cost is slightly over $130,000. Bills for phase 3 are expected late September for certification at the Oct. 26 meeting.

The full story

The director told the board that all phase 2 work on the county’s remaining reconstruction project is done and that phase 3 materials are on site. "We received the last, which was a little over 300 feet of 15 inch tile, about a week ago," the director said. Contractors are expected to begin work around Sept. 1, weather permitting.

The director estimated phase‑3 costs are slightly over $130,000 and said bills for the project will be submitted late September so the board can consider certification at its Oct. 26 meeting. Collections tied to the project are scheduled to begin Nov. 10, 2027; the director projected the reconstruction would be paid off by Nov. 10, 2031, barring changes to scope or schedule.

Written with AI from the event video and transcript. Check it against the source ↓