Board approves $3,500 MRI proposal to widen E3 Basin control structure
Summary
The Board approved MRI Construction Proposal #606 for $3,500 to widen the E3 Basin control structure weir to the maximum width at the FPL easement and asked staff to provide before-and-after photos and consider a manual gate.
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
District Manager Cleo Adams presented MRI Construction Proposal #606 to widen the opening on the E3 Basin control structure. District Engineer Charlie Krebs explained the scope: using a concrete saw to widen the weir to the maximum width toward the Florida Power & Light easement so the community can move more water out of the basin; the Board approved the proposal for $3,500 on a motion by Kurt Blumenthal, seconded by Bob Schultz.
Mr. Krebs agreed to provide before‑and‑after photographs of the control structure and to inquire about installing a manual open/close gate near the control structure. The Board did not add any conditions to the approval beyond the typical contract administration steps.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.