Construction progress reported; commissioners direct scope and RFP work for new building IT

Sep 10, 2024

Court heard a construction update: exterior work nearly dried in, permanent power and windows underway; server room and IT infrastructure were pulled out of the GMP and will require separate RFP/bid materials and possible neutral technical adviser to avoid vendor conflict-of-interest.

The full story

An owners' meeting update described progress at the new county building — curb and gutters, permanent power near completion, window frames installed and exterior 'dried in' anticipated around Sept. 20 — while the court shifted focus to the independent IT and server‑room scope that contractors flagged as outside the GMP.