Bond program manager: high school construction about 30% complete, storm shelter underway
Aug 19, 2025
Cameron Holloman said the 2024 high-school bond construction is roughly 30% complete with underground work largely finished, decking and roof work progressing, and a storm-shelter gym (about 6–7,000 sq ft) under construction; projected phased openings are planned next summer.
The full story
Cameron Holloman, the district’s bond program manager, briefed the board on progress at the 2024 high-school construction project. He said the project is about 30% complete and that approximately 25% of the project budget has been spent to date; several soft-cost items remain to be invoiced.