County reviews inactive solar special exceptions; staff says permits are void under current code
Jun 10, 2026
The board reviewed two previously approved minor solar special exceptions (Muskegee Solar and Shad Solar) and staff reported neither project has commenced construction; planning staff and the county attorney said the permits are void under the county zoning ordinance for failure to commence use.
The full story
Planning staff reported that Muskegee Solar LLC’s SPX‑07‑2021 approval for a 4.9 MW solar project on Balti Road has not progressed to construction since approval, that no site plan or permit activity exists, and that required periodic reviews have not been satisfied. Because the applicant did not commence the permitted use within the timeframe established by county ordinance, staff advised that the special exception is void by operation of the zoning code; the zoning administrator will issue the formal determination.