Commissioners approve change order to use lime fly‑ash mix on Chambers Parkway stabilization
Feb 24, 2026
County staff explained a change-order adjustment to increase lime percentage (from 8% to 10%) and use a lime fly‑ash mix for soil stabilization on Chambers Parkway; commissioners asked for clearer cost breakdowns before approval and then approved the change order.
The full story
County engineering staff described change order No. 4 on the Chambers Parkway project to switch from straight lime stabilization to a lime fly‑ash mix after encountering subsurface issues. Staff said the change involves increasing the lime percentage from 8% to 10% and noted this will add roughly 97 tons of material to the work. One commissioner pressed why an existing line item appeared again in the total; staff said the existing line remains but proposed quantities increased and agreed to provide a clearer breakdown of existing versus proposed costs.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.