Commissioners approve change order to use lime fly‑ash mix on Chambers Parkway stabilization

Feb 24, 2026

County staff explained a change-order adjustment to increase lime percentage (from 8% to 10%) and use a lime fly‑ash mix for soil stabilization on Chambers Parkway; commissioners asked for clearer cost breakdowns before approval and then approved the change order.

The full story

County engineering staff described change order No. 4 on the Chambers Parkway project to switch from straight lime stabilization to a lime fly‑ash mix after encountering subsurface issues. Staff said the change involves increasing the lime percentage from 8% to 10% and noted this will add roughly 97 tons of material to the work. One commissioner pressed why an existing line item appeared again in the total; staff said the existing line remains but proposed quantities increased and agreed to provide a clearer breakdown of existing versus proposed costs.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in