Committee debates making data centers industrial property; size threshold and administrative fixes proposed
Sep 2, 2026
Draft 27LSO111 would classify data processing centers as industrial property. Witnesses warned the definition is broad and could capture small server rooms; lawmakers proposed size or investment thresholds (eventually a 13 MW consumption placeholder) and a suggestion to tie the change to the sales‑tax data‑center exemption. The committee tabled the draft for further work.
The full story
The committee took up draft 27 LSO 1 11, a working draft that would add data processing services centers to the industrial property class for property‑tax assessment.