Evergreen Elementary project ahead of schedule, district told
Aug 17, 2026
Aug 17, 2026
A district project presenter reported that Evergreen Elementary is progressing well: 100% DD sets received, footings poured, prefabrication starting and GMP 3 will be presented at the next board meeting. Staff warned schedule float is tight.
The full story
A construction presenter told the board the Evergreen Elementary project is moving "extraordinarily well," reporting that 100 percent design development documents have been received, footings have been poured across most areas and some wall systems will be prefabricated on-site.