Dubuque County staff outline stormwater limits, warn data centers would drive large detention needs
Aug 12, 2026
County watershed staff said projects that disturb 1 acre or more require a stormwater permit and showed that a hypothetical 420‑acre data‑center campus with ~35% impervious surface would demand millions of cubic feet of detention and extensive treatment infrastructure.
The full story
Eric Schrock, Watershed Program Director for Dubuque County Watersheds, told residents that the county’s stormwater ordinance requires permits for projects that disturb 1 acre or more and that engineers size stormwater systems around three goals: water‑quality volume, channel protection and flood protection. "Projects that disturb 1 acre or more of ground require a stormwater permit," he said during the county’s public engagement meeting.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →