County pauses work on steep Highway 24 driveway; engineering redesign required
Sep 8, 2026
County building staff issued a stop-work order on a Highway 24 South driveway and contracted Marson Engineering to redesign the access. The consultant presented a revised alignment, recommended retaining walls and a 16-foot platform with pullouts, and county staff said final driveway approval will require CDOT coordination and possible variances.
The full story
County planners told commissioners they had placed a stop-work order on a driveway where construction advanced before a certified engineering design was submitted. Marson Engineering presented a revised grading and retaining-wall approach intended to avoid large fill walls and to stabilize slopes; the consultant said the redesign reduced walls and moved the road platform slightly into the hillside. "My name is Tom Morrison. I'm a civil engineer and land surveyor," the consultant identified himself while describing the design choices made to reduce retaining-wall extent.