Baker Road reconstruction update: culverts progressing, additional inspections likely
Jul 21, 2026
Maintenance reported progress on culvert work and clearing for Baker Road reconstruction, but additional inspection costs and contractor documentation (draw requests, lien waivers, bonding) were discussed by the board.
The full story
Chris Klein, maintenance supervisor, reported on Baker Road reconstruction progress including culvert installation and clearing. Klein told the board that additional inspection costs are likely and described the reconstruction schedule; supervisors discussed contractor performance, draw requests, lien waivers and bonding requirements.
The board did not authorize new funds at the meeting but flagged the need for additional inspection spending and contract oversight. Separately, the chip-seal project's fog seal is complete and the board is holding a 5% retainage per the contract until next year.
Written with AI from the event video and transcript. Check it against the source ↓