District reports progress on drainage projects; tree removals and contingency costs noted
Jun 23, 2026
Charlie Krebs said all four drainage sites are under construction with staging, pipe installation and grading; Palmetto Dunes work should finish this week and the project is expected to be complete by end of July, though tree removals and contingency charges (including an accidental AC line hit) were highlighted.
The full story
Charlie Krebs, District Engineer, reported that all four drainage improvement sites are under construction and that silt fences are in place across cleared sites. "All four sites are under construction; sites are cleared and silt fences were installed," Mr. Krebs said, and he outlined timelines: Palmetto Dunes expected to be completed by the end of the week, sod installations in Turnberry and Palmetto Dunes the week of July 2, and pipe installation in Oak Run the week of June 29.