Maple Grove staff proposes financial oversight measures for Community Center Phase Two
May 4, 2026
City staff outlined a Phase Two oversight scope including review of CMAR amendments, evaluation of the Guaranteed Maximum Price agreement, subcontractor selection oversight, and development of pay-application standards and change-order controls, with recommended use in the first quarter of construction and periodic follow-up.
The full story
City Administrator Heidi Nelson presented a proposed scope of financial oversight for Phase Two of the Maple Grove Community Center Renovation and Expansion project at the May 4 work session. Nelson outlined measures she said would strengthen controls during construction: review of Construction Manager at Risk (CMAR) agreement amendments, evaluation of the Guaranteed Maximum Price (GMP) agreement, oversight of subcontractor selection, and development of pay-application standards and change-order controls.
