River Ridge CDD approves $1.11 million drainage contract with 5% extra contingency

Apr 28, 2026

The River Ridge Board awarded Clark Construction Group a not-to-exceed $1,111,860 contract for four stormwater phases after adding a 5% contingency to cover unknowns; Oak Run HOA connection costs were identified as optional at $197,201.47.

The full story

The River Ridge Community Development District Board of Supervisors voted unanimously to award a four‑phase stormwater management contract to The Clark Construction Group, Inc., in a not‑to‑exceed amount of $1,111,860, which includes an added 5% contingency to cover unforeseen unit costs.