County staff report progress on three bridge projects; paving could reopen Bridge 105 this week
Sep 9, 2026
Sep 9, 2026
County staff described recent work on three active bridge projects, including membrane installation and imminent paving for Bridge 105, pile removal and coating for Bridge 58, and concrete-mix adjustments on Bridal 142 to avoid gaps under steel reinforcement.
The full story
Nate, a county staff member overseeing public-works projects, told the commissioners that crews installed falsework on the north side of Bridal 142 last Friday and adjusted the concrete mix to avoid gaps beneath steel reinforcement.