Board hears timeline, bid dates and May 2028 completion target for Rockingham Technical Center
Aug 25, 2026
Aug 25, 2026
Mr. Reed briefed the board on architect renderings and a procurement timeline for the Rockingham Technical Center, with bids due Sept. 24 and planned substantial completion May 5, 2028 and final completion May 19, 2028.
The full story
Mr. Reed presented architect renderings and a timeline for the Rockingham Technical Center. He said the bid package will be posted this week, a pre-bid meeting is scheduled for Sept. 10, bids are due Sept. 24, and the board could consider a recommendation at the Sept. 28 meeting.