County says closed‑loop cooling will be required in draft data‑center ordinance

Jul 29, 2026

Staff told residents the county intends to require closed‑loop cooling, independent hydrogeologic studies and wastewater plans before occupancy, and cited an example closed‑loop data center reporting a $60 monthly water bill.

The full story

At an extended presentation after the formal meeting, county staff said closed‑loop cooling will be a required element of any data‑center ordinance to prevent ongoing withdrawal of groundwater. Miss Dukes described closed‑loop systems as those that ‘‘do not discharge into a wastewater system’’ and said the county will require independent hydrogeologic studies that estimate annual water usage and explain wastewater handling before a certificate of occupancy is issued.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.