Audit: Taylor County CO projects show small overrun but $217,000 contingency surplus
Apr 7, 2026
Apr 7, 2026
The county auditor reported $11.5 million in CO proceeds and $11.58 million in projected project costs, noting a roughly $217,000 surplus available from unused contingency and interest; outstanding items include vehicle-storage and training building costs.
The full story
County auditor Mr. Anderson briefed the Commissioners Court on the status of certificate-of-obligation (CO) projects and balances, providing a one-page summary of projects, expenses in FY25 and FY26, and remaining balances.