City manager warns developer nonresponse may trigger STP action after plan differences

Sep 9, 2026

City manager Hoffman told council staff had not received a developer response to a $2 million offer and that submitted lake construction drawings reduced depth from 12 to 8 feet; staff noted revocation of the site development plan is not automatic and further council action may be required after the Sept. 12 deadline.

The full story

City manager Hoffman updated council on a pending site-development-plan matter with a Sept. 12 submission deadline. Hoffman said staff had not heard from the developer since a July 13 acknowledgment and that construction drawings submitted in the second submittal indicated a lake depth of 8 feet rather than the 12 feet originally specified.