Commission approves $2,714 change order for sheriff's interview-room recording system

Cole County Commission · June 18, 2025

Summary

The commission approved Change Order No. 1 to add two 24-port PoE switches with SFP modules for $2,714 to the sheriff's interview-room recording system to provide additional ports and an isolated network.

The Cole County Commission approved Change Order No. 1 for project 2025-17, the sheriff's interview-room recording system, to purchase two 24-port PoE switches with single-mode SFP modules for $2,714. Staff said the additional hardware is needed because the project required more network ports than originally anticipated and the county prefers the system run on an isolated network.

"So I have a change order requesting the purchase of 2 access 24 port PoE switches with 2 single mode SFP modules for a purchase price of $2,714," a staff speaker explained. Commissioner (speaker 5) moved to approve the change order, another commissioner seconded, and the motion passed on a voice vote. The commission directed staff to complete the procurement so the recording system can operate as specified.

The procurement is intended to avoid future integration and security issues by keeping the interview-room system separate from the county's general network and to ensure sufficient ports for forthcoming devices.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source