Developers outline capital‑stack options as $5 million gap persists
Dec 18, 2025
Dec 18, 2025
Developers said they are reworking the Munising Marketplace capital stack after MEDC tools proved unavailable, outlining a 1% low‑interest loan up to $1.5 million, a deferred developer fee over $500,000 and an equity raise as options to close the project shortfall.
The full story
Shannon Morgan, partner at Radivari Development, and consultant Jennifer Acosta said the Munising Marketplace team is recirculating a pro forma and seeking replacement financing after most state MEDC tools proved unavailable. Morgan said the group resubmitted the project as a transformational brownfield but was told CRP and related programs could not be committed now.