Draft CUP rules add decommissioning and e‑waste requirements for data centers
Jun 23, 2026
Butler County's draft regulations add a decommissioning plan requirement including equipment removal, demolition, revegetation and financial security; staff discussed requiring recycling plans and prohibiting landfill disposal of retired equipment as a CUP condition.
The full story
County counsel said the draft would require a decommissioning and site restoration plan describing equipment removal, battery and fuel disposal, demolition, grading and revegetation. The plan would also include financial assurance to support decommissioning work and site restoration if a facility is abandoned or retired.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
