Draft requires expanded application checklist and county‑selected third‑party reviews
Jun 23, 2026
The draft application adds classification fields (power demand, building square footage, acreage), requires a host of studies (water, traffic, noise, hazardous materials, energy usage), and asks applicants to deposit funds for county‑selected third‑party reviews of those studies.
The full story
County staff walked the boards through proposed changes to the CUP application form and the core submittal checklist. The form will include a data‑center classification checkbox and specific data fields — power demand/capacity, cumulative building square footage and project acreage — to allow staff to cross‑check classification and determine appropriate review and deposit amounts.
Counsel read the proposed deposit language: "Applicant must deposit funds for county selected 3rd party review of water, energy, noise, traffic, environmental, fiscal, emergency response, and decommissioning studies. The consultant shall be selected by the county, not the applicant." Staff said the goal is to ensure independent technical review when projects could affect county infrastructure or services.
The transcript lists required studies: water‑use feasibility, traffic‑impact, noise/vibration, stormwater/erosion/floodplain, utilities and infrastructure letters, fire and life safety, hazardous‑materials management and inventory, air‑quality emissions, construction management, emergency response coordination and an energy usage plan. Commissioners discussed practical timing and whether smaller modular or edge facilities should be exempted from some studies.