Public works: CR 100N & Raceway roundabout moving ahead; Dan Jones projects face utility delays

Avon Town Council · September 10, 2026

Summary

Public Works Director Steve Moore reported the CR 100N & Raceway roundabout will receive asphalt soon with completion targeted by October; Dan Jones Phase 3 remains pending AT&T line relocation while Phase 4 design will be bid in spring.

Public Works Director Steve Moore told the council the CR 100N and Raceway roundabout "is moving along with asphalt coming soon," with the aim of completing paving by the end of October.

Moore said Dan Jones Phase 3 is still waiting on AT&T to move utility lines and that Dan Jones Phase 4 design is nearly finished and scheduled to go to bid in the spring. He reported CCMG 2026 is nearly complete, CCMG 2027 submissions are due by the end of September, and that staff filled 36 potholes, completed 104 inspections and issued $7,000 in fines. The Dan Jones Bridge project was described as expected to finish by the end of November.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source