Engineering updates: bridge work, Mill Hill reopened and airport projects move forward
May 28, 2026
County engineers reported permit submittals and federal reviews for a County Route 7 bridge project, said Mill Hill bridge work finished May 8, outlined a public hearing on right‑of‑way acquisition for County Route 7 on June 27, and introduced airport consultant agreements tied to $2 million‑plus in requests.
The full story
Engineering staff told supervisors they submitted permit applications for County Route 7 (Punds Creek) to the Army Corps and NYSDOT and that they expect to use existing abutments while replacing the superstructure if permitted. “We anticipate utilizing the existing abutments and just replacing the superstructure,” the engineering official said, adding that federal and state reviews will influence final design.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
