Board approves $3,500 MRI contract to widen E3 Basin control structure opening

Mar 24, 2026

Supervisors authorized MRI Construction Proposal #606 to widen the E3 Basin control-structure opening to maximize outflow; contract approved for $3,500 and staff will provide before-and-after photos and evaluate a manual gate option.

The full story

Mrs. Adams presented MRI Construction Proposal #606 on March 24 to widen the opening on the E3 Basin control structure so the weir reaches its maximum width and improves outflow to an FPL easement. The work would use a concrete saw to widen the weir, and the board discussed whether a manual open/close gate could be added.