Board hears construction update: Tularosa Middle School about 35% complete

Sep 10, 2026

Architects and the contractor told the Tularosa Municipal Schools board the new middle school is roughly 35% finished, with framing, slabs and upcoming structural steel work; a "topping out" ceremony is planned for mid-October.

The full story

The Tularosa Municipal Schools board received a construction progress report on the new Tularosa Middle School. Juan Durable of Decker, introduced by Superintendent Montoya, said the district issued the notice to proceed on 2026-03-30 and that "the project is about 35% complete." Bradbury'affiliated construction staff described ongoing framing and slab work, imminent roofing and structural steel, and finishing of the CMU gym wall.