Pumping Station project slips; council tables $80,430 inspection amendment pending USDA documentation

Nov 5, 2025

GMB engineers told the council substantial completion is now likely in January 2026. An amendment for up to $80,430 for USDA-required full-time inspection services was presented and tabled pending written documentation from USDA.

The full story

GMB engineers Jason Lytle and Andrew Lynch updated the Trappe Town Council on Nov. 5 that the Pumping Station project, originally scheduled for substantial completion on Nov. 29, 2025, is running behind and now appears likely to finish in January 2026. The delay prompted GMB to present an amendment to the owner-engineer agreement for additional full-time inspection services as required by USDA.