Webster renovation near completion; district plans December move‑in for Section A
Summary
The district reported the Bartlett renovation is about 94% complete, with Section A move‑in targeted for the end of December and remaining site work through next June. Officials said $140,000 in retainage remains for punch‑list items.
Director of Finance and Operations Conjo told the committee the Bartlett renovation is “94% complete,” with an expected move‑in for Section A at the end of December and final site work wrapping up next June.
Conjo said casework installation, bathroom tile and painting are underway, playground installation for preschool will begin next week and contractors expect to remove construction trailers in October. She reported a retainage hold of about $140,000 to finish remaining punch‑list items and said warranty rolloffs will be staggered by building section. “We are 94% complete,” Conjo said. The district plans a school‑building committee walkthrough next month and can arrange a separate walk for the school committee.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.