SDDOT reports July change‑orders net decrease of $2.48M; approves several structure bids
Summary
The Department reported July Construction Change Orders produced a net decrease of $2,478,472.32 and a 12‑month net contract change of +1.39%; the Commission also approved several structure and maintenance bids, including Lehtola Builders low bid of $544,416.03.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
Ryan Johnson told the Commission that CCOs completed in July resulted in a decrease of $2,478,472.32 to original contract amounts, while over the past 12 months the total change to original contracts increased by 1.39%.
Johnson highlighted specific project CCOs: IM 0293(113)78 (Minnehaha County, I‑29 structures near Skunk Creek) had CCO No. 6 adding $283,660.53 (3.8%) for adjusted as‑built quantities and extra work; IM‑B‑CR 2292(101)3 (I‑229 Exit 4 Cliff Avenue) had CCO No.11 adding $209,419.78 to change a sign cantilever to a double beam sign bridge; and NH‑PH 0385(50)96 (US385/Pactola Dam area) had CCO No.4 adding $127,718.69 for additional asphalt to smooth selected locations.
Separately, Sam Weisgram presented bid letting results. Notable low bids approved Aug. 19 included Lehtola Builders, Inc. at $544,416.03 for BRO‑B 8055(37) structure work in Roberts County and $434,406.84 on BRF‑B 6202(07). The Commission approved listed bids by roll call vote. On Aug. 25, 2026 the Commission also approved a bridge‑cleaning bid of $63,994.50 to Sir Lines‑A‑Lot for Pierre regionwide work.
The record shows routine contract quantity adjustments and targeted extra work as the principal drivers of the reported change‑orders.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.