Council approves layout for $6.61M Dunkirk Lane reconstruction project

Mar 16, 2026

Council adopted Resolution No. 26-048 approving final layout and ordering plans and specifications for Dunkirk Lane Street and Utility Project No. 27-05, a full roadway reconstruction with estimated cost of $6,610,000 funded through reconstruction fund, special assessments and trunk/utility funds.

The full story

City Engineer R.J. Kakach presented a preliminary design and layout for Dunkirk Lane Street and Utility Project No. 27-05, explaining that Castlewood Estates roadways are in poor condition and full reconstruction is recommended for 2027. The preliminary engineer’s estimate for the project is $6,610,000, and the scope includes concrete curb and gutter, extended public utilities, a trail addition per the trail master plan, and trunk watermain installation along Arbor Ridge Parkway.