District facilities update: playgrounds finished, stadium and elementary projects ongoing

Dec 16, 2025

Executive Director Brent Stanford told trustees several playgrounds are complete, the softball complex is near completion and the baseball complex is about halfway done; larger projects with architects Corgan and Joris aim for fall 2027 completion.

The full story

Brent Stanford, executive director of support services, briefed the board on district construction projects. He said Eastridge, Shutman, Wooden and Shields playgrounds are complete, Red Oak Elementary is about 25% finished, the softball complex is approximately 90% complete and the baseball complex is about 50% complete. "Right now, we're on schedule," Stanford said, and added the district is coordinating with architects Corgan and Joris on larger projects.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in