County reports paving and small-structure progress: County Road P complete, County Road E paving imminent
Aug 18, 2026
Commissioner Brian Trebiatowski reported progress on several projects: I‑39 southbound work nearing completion, County Road P complete awaiting pavement marking, County Road E paving to finish within a week, and town paving work continuing in Newton, Harris and Mecan.
The full story
Highway Commissioner Brian Trebiatowski provided a multi-level project update. At the state level, I‑39 southbound south end was noted as nearing completion and north end work would soon begin on erosion control, staking and paving preparation. At the county level, the County Road P project is complete and awaiting pavement marking; County Road E (STP‑Rural) paving was expected to be completed within a week, with guardrail and landscaping to follow by the end of the month.