Selectboard authorizes final change orders and deems town office substantially complete

Londonderry Selectboard · July 22, 2025

Summary

Board authorized several change orders for the town office renovation (concrete steps removal, porch ceiling, water line, site work, solar addition) and noted the project is substantially complete with minor punch-list and warranty items remaining.

Board members reviewed outstanding change orders for the town office renovation and moved to authorize five items: removal of concrete steps on the south side ($2,269), entry porch ceiling replacement for lighting ($589), replacement of the well water line ($805), additional miscellaneous site work ($24,137), and a solar-size addition ($626). The motion to authorize the change orders was seconded and approved by voice vote.

The board then reviewed the project's punch list and concluded the town office is substantially complete; painters remain on site and a few lock and adjustment items persist. Members noted the standard warranty period and that final payments may be made while retaining the ability to require repairs for faulty workmanship or materials during the warranty.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source