Evergreen Elementary on schedule; GMP 3 to be presented at next board meeting

Enumclaw School District Board · August 17, 2026

Summary

A project presenter told the board that Evergreen Elementary construction is progressing — footings poured, prefabrication starting, and a full project GMP (GMP 3) will be brought to the next meeting. Construction documents target 90% by Oct. 19 and 100% by mid–late December.

The board heard an update on Evergreen Elementary construction: the presenter reported the project is moving along, with footings poured in most areas, on-site wall prefabbing planned, and early foundations expected to start in August. The presenter said the team has executed three contract amendments to date and that GMP 3, which will encompass the entire project budget, will be presented to the board at the next meeting.

On design and schedule the presenter said 90% construction documents are due Oct. 19 and 100% documents should be mid-to-late December; the presenter also said the school “will accommodate the appropriate number of students. I believe 600.” Board members asked for renderings (available on the district website) and confirmed that commissioning will be performed before occupancy and continued during early use to ensure systems operate as intended.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source