Evergreen Elementary on schedule; GMP 3 to be presented at next board meeting

Aug 17, 2026

A project presenter told the board that Evergreen Elementary construction is progressing — footings poured, prefabrication starting, and a full project GMP (GMP 3) will be brought to the next meeting. Construction documents target 90% by Oct. 19 and 100% by mid–late December.

The full story

The board heard an update on Evergreen Elementary construction: the presenter reported the project is moving along, with footings poured in most areas, on-site wall prefabbing planned, and early foundations expected to start in August. The presenter said the team has executed three contract amendments to date and that GMP 3, which will encompass the entire project budget, will be presented to the board at the next meeting.