MLP Manager Michael Slowinski told the Select Board the municipal broadband operation has about 660 active subscribers, incurred roughly $18,000 in winter damage repairs, and has sufficient funds to cover a $153,000 bond payment; pole replacements and reimbursements from Eversource remain pending.
The full story
MLP Manager Michael Slowinski updated the Select Board on operations, repairs, collections, and near-term financial obligations for Colrain's municipal light and broadband plant.