Ringgold County engineer reports progress on chip seal, mowing and bridge work
Sep 14, 2026
Sep 14, 2026
Engineer Jared Johnson told the board crews have been mowing roadsides, hauling Farm-to-Market rock, spraying brush at bridge ends and conducting chip-seal work on J55; trucking issues delayed oil delivery and about 5,400 lane feet remain to complete the J55 chip seal.
The full story
County Engineer Jared Johnson updated the Board on secondary-roads operations, saying crews were mowing vegetation along paved roadsides and Farm-to-Market gravels in the southwestern portion of the county and hauling rock to south central and southwest maintainer districts.