Council tables Control Building award after bids exceed budget

Sep 16, 2025

Brundidge councilors voted unanimously to table awarding Contract 2 (Control Building) at the wastewater plant after bids came in over budget; the item will be revisited after further research.

The full story

During the Sept. 16 meeting Councilmember Hall moved to table awarding Contract 2 for the wastewater plant's Control Building after bids were reported to be over budget. Mr. Gaynor seconded; the motion carried with all voting yea (4-0), Holland absent.

The minutes state: "Due to bids coming in over budget for the Control Building at the wastewater plant, Mrs. Hall moved to table the awarding of Contract 2 until further research can be considered." The council did not discuss specific alternate funding sources or a rebid schedule during the meeting, leaving next steps for staff follow-up.

Written with AI from the event video and transcript. Check it against the source ↓