River Ridge details drainage work in four neighborhoods, targets end‑of‑July completion

Jun 23, 2026

District engineer reported all four drainage sites are under construction with pipe and grading work underway; staff expect completion by the end of July and will track contingency costs from unexpected repairs.

The full story

Charlie Krebs, the District Engineer, briefed the Board that "all four sites are under construction," with clearing and silt fences in place, fill staged at Turnberry, pipe installation in Oak Run planned the week of June 29, and sod installation in Turnberry and Palmetto Dunes the week of July 2. He told the Board that Palmetto Dunes will require removal and replacement of a total of twelve trees (mostly slash pines and two red maples) and that declining Royal Poinciana trees will be replaced.